Where does every $100 of your data centre go?
Upload a budget, an EPC tender or a capex quote. See each line against the market, with a confidence score on every number.
CYour $100 · 40MW, air and liquid cooling, JohorExample data
LineYoursMarketVerdictConf.
Electrical (switchgear, UPS, transformers)$38.20$31 to 36Above market82
Mechanical (cooling)$19.60$18 to 23In line77
Building shell and civils$14.10$13 to 17In line84
Grid works and substation$7.40$6 to 11In line61
On-site generation (backup)$6.90$5 to 8In line73
Fees and design$5.30$5 to 8In line70
Contingency$2.10$4 to 7Light: risk68
Other and unmapped$6.40n/aUnmapped: 3 linesn/a
Market band in $ of every $100, from comparable projects. Confidence 0 to 100.
Your total against the market. $9.8m/MW, 64th percentile.
Of 31 comparable projects in South East Asia, 2024 to 2026. Electrical is $4.20 of every $100 above the market median. Your 22 months from notice to proceed to energised is 3 months faster than 80% of similar projects.
Get the full report →CProgramme · 22 monthsExample data
Notice to energised22 months, 3 months faster than 80%
Likely slipTransformers: 30 to 48 months to order
The Casitel Cost Index. Cost to build per MW of IT load
MarketMedian $m/MWMonths to energiseProjectsConfidence
Malaysia (Johor)9.4241774
Japan (Tokyo, Osaka)12.8301269
India (Mumbai, Chennai)7.1261466
Saudi Arabia10.628652
Germany (Frankfurt)12.2291578
Kazakhstanmodelledmodelled221