Where capital discovers digital infrastructure.

State your mandate in a sentence. See the deals that fit, scored on power, price and sponsor. Read what the people who build the market see first.

State your mandate
Unlock deal flow

Unlock the names, the diligence pack and a weekly feed against your mandate. Verified investors only.

What the people who build the market expect. The Casitel Pulse, October 2026

Six questions, two minutes, once a month, from verified operators, developers, lenders and investors.

8.1%

Cost of capital, next 12 months

+15 bp on September
6.4%

Stabilised cap rate expected

GCC 6.9%, Europe 5.8%
+6%

Wholesale rent change per year

Next 2 years
4.2 yrs

Typical time to power

50MW, all regions
Power

Biggest constraint

61% of respondents
[N]

Respondents

Verified, 28 countries

Give two minutes →

Field notes from inside the business.

WhenNoteStatus
2 Nov · GBA DNO is now quoting 2031 for new 100MW connections at two substations near the M4. Utility engineer.Confirmed
1 Nov · UAETwo operators report transformer lead times past 70 weeks for 132kV units. EPC.Claim, 2 sources
30 Oct · NordicsA hyperscaler is assembling land around a grid node in central Sweden. Broker.Claim, checking

Post a field note →